Harbor Pointe Townhomes Moves Into Site Development

November 2, 2026

Site development is underway at Harbor Pointe Townhomes, a planned 79-unit community along Loch Lomond Drive in Greensboro.

Fortis Siteworks is delivering the civil site-development package for the project, with crews performing survey layout, erosion-control installation, temporary sediment ponds, mass grading and preparation for future roads, utilities and townhome pads.

The roughly 15-acre development will require approximately 53,000 cubic yards of earthwork and more than 10,000 linear feet of underground infrastructure, including storm drainage, water and sanitary sewer systems.

The underground scope includes approximately 2,600 linear feet of storm pipe, more than 2,500 linear feet of water main and more than 5,200 linear feet of gravity sewer and force main. The work also includes fire hydrants, water-quality units, road-crossing casings and utility services supporting the future townhomes.

Roadway construction will include approximately 4,750 linear feet of curb and gutter, more than 3,500 square yards of aggregate base and asphalt paving, and retaining-wall support throughout the community.

Temporary sediment ponds, silt fence, inlet protection and other erosion-control measures are helping manage stormwater runoff while site development advances. Those controls are an important early step before major grading and utility installation can move across the property.

Fortis is working with The Macallan Group and Greyden Engineering to move Harbor Pointe from initial development into a fully served residential community at Lake Oconee.